Plans for next week:

  • Continue working on integrating individual modules with the parallel communication network.

  • Test algorithms of the completed modules.

  • Begin mounting platforms onto car for circuitry and touchscreen

Group Meeting memo:

  • Discussed the progress made with individual modules and user interface.

  • Discussed method of mounting the circuitry in the car.

Project Progress

Quinn:

  • Finalized GPS algorithm for testing.

  • Worked on NAV central module algorithm.

  • Worked on control modules testing algorithm for the GPS NAV system.

  • Finalized concept of pixel detection for camera assisted GPS error reduction.

Jacob:

  • Worked on intercommunication between different modules and the number of bits that would be used for each.

  • Work on wiring the ultrasonic module and starting to position the three ultrasonic sensors on the car.

  • Will start to implement controlling the servo by communicating from the auto-parking module to the main controller

Jordyn:

  • Worked with Machine Shop on platforms for circuitry and touchscreen

  • Worked on updating User Interface functionalities

  • Next Week: Mounting platforms onto car and continue working on User Interface

DJ:

  • Researched 12V rechargeable batteries to power the car's touchscreen.

  • Next week: Begin positioning the LiDAR sensor onto the car; Finalize the ACC algorithm and prepare for testing.

 
 
 

Recent Posts

See All
Week of 4/11/2022 - Weekly Report 24

Plans for next week: Continue working on integrating individual modules with the parallel communication network. Test algorithms of the...

 
 
 

Comments


Post: Blog2_Post
  • Facebook
  • Twitter
  • LinkedIn

©2021 by Jacob Longo. Proudly created with Wix.com

bottom of page